Home breadcru News breadcru Company breadcru Furnace to raise ethylene production capacity at Kazanorgsintez

Furnace to raise ethylene production capacity at Kazanorgsintez

25 Sep '07
2 min read

This process will let begin “Technip” furnace operation and put into operation cracked gas preparation unit E-500. So it will reduce commissioning works, planned for 2008, according to design of ethylene plant revamp.

Now assembly of equipment, which is supplied for E-500 construction completion by stages, is in process. It includes equipment for E-500 gas separating sections and reinstalled cold box “Ethylene-100” (where, according to design, methane-hydrogen cut with minimum ethylene loss will be produced from cracked gas).

Moreover, according to creation plan of the unit E-500, pipes parts tie-in in existing technological pipelines was arranged during overhaul of the Ethylene plant this year.

It will provide startup of the “Technip” furnace and operation of the complex E-500 (with minimum stand time for ethylene production).

Kazanorgsintez

Get Free Weekly Market Insights Newsletter

Receive daily prices and market insights straight to your inbox. Subscribe to AlchemPro Weekly!